Name of Project

General Railway Organization in Jakarta

Total Investment

Rp 7.345 Trillion

Description

General Railway in the Province of Special Capital Territory of Jakarta (DKI Jakarta) will build 7 corridors of LRT Jakarta.

Latest Status

Construction and will be operation in 2019

  • Public hearing was held on 12 May 2016 (East Jakarta) and 25 May 2016 (North Jakarta).
  • Work contract P101/corridor 1, has commenced on 22 Juni 2016 (at the Commemoration of Jakarta Anniversary) which includes preparation, green areas determination, traffic management, etc.
  • Currently, tracing process is underway. A sketch map for road axis determination to obtain approval is in the verbal process at the relevant Technical Agencies, namely Transportation Agency, City Planning and Jakarta City Administration

Location

Tangerang, Banten

Source Budget

Funding Scheme

State-Owned Enterprise

Project Owner

Jakarta City Administration

Planned Commence Date

2016

Planned Commercial Operation

2019