Name of Project

Balikpapan-Samarinda Toll Road (99,35km)

Total Investment

Rp 9,970 Trillion

Description

The 99,35 km long toll road will connect two biggest cities in East Kalimantan, namely Balikpapan and Samarinda. This project is divided into two Sections, i.e., Section 1 which consists of Package 1 (25,07 km) and Package 5 (11,09 km) and Section 2 which consists of Package 2 (23,26 km), Package 3 (21,9 km) and Package 4 (17,7 km).

Latest Status

Land Procurement :
Section 1: Balikpapan KM 13 – Samboja (APBD) : 95,16%
Section 2: Samboja – Muara Jawa : 95,69%
Section 3: Muara Jawa – Palaran : 93,49%
Section 4: Palaran – Samarinda : 46,81%
Section 5: Balikpapan –Sepinggan Airport
(APBN-Loan China) : 59,09%
Construction :
Section 1: Balikpapan KM 13 – Samboja (APBD) : 53,87%
Section 2: Samboja – Muara Jawa : 0%
Section 3: Muara Jawa – Palaran : 0%
Section 4: Palaran – Samarinda : 0%
Section 5: Balikpapan –Sepinggan Airport
(APBN-Loan China) : 0,82%

Source Budget

State Budget

Funding Scheme

Private

Planned Commence Date

2017

Planned Commercial Operation

2019

  • Services Publication
  • Industry Publication
  • Tax Regulation Update

South Quarter, Tower B, Mezzanine Level, Jl. R.A. Kartini Kav. 8, RT.10/RW.4, Cilandak, Jakarta 12430
Ph: +62 815 629 0000

Workshop: Kavling Polri Blok F8, Jalan Hadiah Utama II No. 1585A, Jelambar, Jakarta

Close Menu
×
×

Cart

WhatsApp chat